Table of Contents
2.......... Project Information
2.3 Construction
Programme and Activities
2.5 Status
of Environmental Licences, Notification and Permits
3.......... Environmental
Monitoring Requirements
3.1 Construction
Dust Monitoring
3.2 Construction
Noise Monitoring
3.3 Construction
Water Monitoring
4.......... Implementation Status of
Environmental Mitigation Measures
5.......... Monitoring Results
5.1 Construction
Dust Monitoring
5.2 Regular
Construction Noise Monitoring
5.3 Construction
Water Monitoring
6.......... ENVIRONMENTAL SITE INSPECTION AND
AUDIT
7.......... Environmental
Non-conformance
7.1 Summary
of Monitoring Exceedances
7.2 Summary
of Environmental Non-Compliance
7.3 Summary
of Environmental Complaints
7.4 Summary
of Environmental Summon and Successful Prosecutions
8.1 Construction
Programme for the Next Three Month
8.2 Key
Issues for the Coming Month
8.3 Monitoring
Schedule for the Coming Month
9.......... ConclusionS AND RECOMMENDATIONS
List of Tables
Table 2.1.......... Construction
Activities in the reporting month
Table 2.2.......... Contact Information of Key Personnel
Table 2.3.......... Status of Environmental Licenses,
Notifications and Permits
Table 3.1 ........ Air Quality Monitoring Equipment
Table 3.2 ........ Location of Construction Dust Monitoring Station
Table 3.3 ........ Noise
Monitoring Parameters, Frequency and Duration
Table 3.4 ........ Noise Monitoring Equipment for Regular Noise
Monitoring
Table 3.5 ........ Noise
Monitoring Stations during Construction Phase
Table 3.6 ........ Noise
Monitoring Parameters, Frequency and Duration
Table 3.7 Water Quality
Monitoring Equipment
Table 3.8 Impact Water
Quality Monitoring Stations
Table 3.9 Water Quality Monitoring Parameters,
Frequency and Duration
Table 4.1.......... Status
of Required Submission under Environmental Permit
Table 5.1 ........ Summary
of 24-hour TSP Monitoring Result in the Reporting Period
Table 5.2 ........ Summary
of 1-hour TSP Monitoring Result in the Reporting Period
Table 5.3 ........ Summary
of Construction Noise Monitoring Results in the Reporting Period
Table 5.4 Summary of Impact Water Quality
Monitoring Results
Table 5.5 Summary of Water
Quality Exceedances
Table 6.1 ........ Observations
and Recommendations of Site Audit
Table 8.1.......... Construction
Activities in the coming three month
List of Figures
Site Layout Plan |
|
Location of Air Quality Monitoring Station |
|
Locations of Noise Monitoring Station |
|
Locations of Water Monitoring Station |
List
of Appendices
Construction Programme |
|
Project Organization Structure |
|
Implementation Schedule of Environmental Mitigation Measures |
|
Summary of Action and Limit Levels |
|
Calibration Certificates of Equipment |
|
EM&A Monitoring Schedules |
|
Air Quality Monitoring Results and their Graphical Presentations |
|
Noise Monitoring Results and their Graphical Presentations |
|
Water Monitoring Results |
|
Detail of Water Quality Exceedance |
|
Event and Action Plan Cumulative Statistics on Complaints, Notification of Summons and
Successful Prosecutions |
|
Monthly Summary Waste Flow Table |
Central Kowloon Route
– Kai Tak West (CKR-KTW; Contract No. HY/2014/07) (hereafter called “the
Project”) covers part of the construction of the Central Kowloon Route (CKR).
The Project comprises
the follow works:
·
50x30m
access shaft with noise enclosure at Ma Tau Kok
(MTK);
·
100m long
cut-and-cover (C&C) tunnel at MTK;
·
Demolition
and re-provisioning of MTK Public Pier;
·
160m long
underwater tunnel (UWT) (Stage 1);
·
210m long
UWT (Stage 2);
·
60m long
C&C tunnel at Kai Tak;
·
130m long depressed
road and 200m long underpass at Kai Tak;
·
390m long
underground tunnel ventilation adit at Kai Tak;
·
Seawall
demolition and construction of new landing steps; and
·
Barging
Point enclosure and conveyor system.
The EM&A programme commenced on 4 April 2018.The impact EM&A for the Project includes air
quality, noise and water quality monitoring.
This is the thirtieth
monthly EM&A Report presenting the EM&A works carried out during the
period between 1 and 30 September 2020. As informed by the Contractor, major
activities in the reporting period were:
Locations |
Site Activities |
Kai Tak |
·
Casting tunnel wall at underpass and ventilation adit; ·
Base slab and wall, roof slab construction at underpass and
depressed road; ·
Backfilling at Underpass ·
Removal of ELS at underpass and depressed road; ·
Falsework erection at underpass |
Ma Tau Kok |
·
TTM implementation; ·
Pipe piling works for cut and cover tunnel; ·
Rock Excavation; ·
Shotcreting at the Access Shaft; ·
Fresh water pipe installation works; ·
Backfilling at Covered Walkway |
Kowloon Bay |
·
Excavation for Stage 1 underwater tunnel; ·
S6 Truss fabrication and installation; ·
Concrete packing between wailing and CPP Wall; ·
Roof slab and base slab construction ·
Waterproofing application; ·
Removal of gas pipe line |
Barging Point |
·
Barging point operation (Spoil Disposal) |
Breaches of Action and Limit Levels for Air Quality
All 24-hour TSP result was below the Action
and Limit Levels at all monitoring locations in the reporting month.
All 1-hour TSP result was below the Action and
Limit Levels at all monitoring locations in the reporting month.
Breaches of Action and Limit Levels for Noise
Regular Noise Monitoring
Four (4) noise-related complaints were
received in the reporting month. However, one complaint received from the
Environmental Protection Department on 23 September 2020 was considered as
additional information for detail of complaint about the closed cases in August
2020 due to a similar investigation for complaint had already been conducted.
The investigation report was updated on 29 September 2020. Based on the
investigation result from other finalized investigation reports, proper
implementation of mitigation measures during the non-restricted hours and
comply with the condition of valid Construction Noise Permit during the restricted
hours. Also, there is no non-compliance recorded based on the result of daily
noise monitoring. Therefore, three action levels of construction noise were
triggered, and the investigation reports were finalized on 18 September, 7 and
8 October 2020.
Breaches of Action and Limit Levels for Water
No Action level and Limit level exceedance were recorded at measured DO in
the reporting month and Total PAHs until 23 September 2020.
Four (4) Action Level and eight (8) Limit level
exceedances were recorded at measured turbidity level in the reporting month.
Eight (8) Action Level and four (4) Limit
Level exceedances were recorded at measured SS level in the reporting month.
Five (5) Action Level and (1) Limit Level exceedances
were recorded at measured Copper Level until 23 September 2020.
Some of laboratory results of Copper and
Total PAHs in September 2020 were in progress, the summary for those parameters
will be reported in next reporting period.
Based on the findings from the completed IRs
on 11, 14 and 18 September 2020, the exceedances were unrelated to the Project.
Except for the exceedances on 21, 23, 25 and 28 September 2020, where
the investigation is undergoing and the investigation
results will be presented in the next monthly EM&A report. Nevertheless,
the Contractor was reminded to ensure provision of ongoing maintenance to the
silt curtains.
Complaint, Notification of Summons and Successful Prosecution
Four (4) complaints were received in the
reporting month. However, one complaint in noise (received by Environmental
Protection Department on 23 September 2020) was considered as additional
information for detail of complaint about the closed cases in August 2020 due
to a similar investigation for complaint had already been conducted. The closed
investigation report was updated on 29 September 2020. Two of the complaints in
noise (received by the Highway Department on 3 September 2020 and Gammon
Construction Limited on 24 September 2020) were referred by the Contractor on 4
September 2020 and 26 September 2020. Those investigation reports were
finalized on 18 September 2020 and 7 October 2020. One of the complaint in air,
odor nuisance, and noise (received by 1823 Government Hotline, Gammon
Construction Limited, and Environmental Protection Department on 17, 23, 24,
and 25 September 2020) was referred by the Contractor on 26 September and 7
October 2020, the investigation report was finalized on 8 October 2020.
No environmental related notification of summons and successful prosecution
were received in the reporting month.
Reporting Changes
No report changes in the reporting period.
Future Key Issues
Key issues to be
considered in the next three months included:
Locations |
Site Activities |
Kai Tak |
·
Base slab and wall,roof slab construction at cut &
cover, underpass and depressed road; ·
Backfilling works and ELS removal at cut & cover,
underpass and depressed road; ·
Dismantle of working platform |
Ma Tau Kok |
·
TTM implementation; ·
Rock excavation; ·
Pipe piling works for cut and cover tunnel; ·
Fresh water pipe installation works; ·
Constrcution of MTK east wall; ·
Constrcution of traffic deck; ·
Covered walkway construction ·
Relocation of MTK public pier |
Kowloon Bay |
·
Backfilling and ELS removal works; ·
Roof slab, base slab and wall construction; ·
Removal of gas pipe line; ·
Waterproofing application |
Barging Point |
·
Barging point operation (Spoil Disposal) |
·
Section 1:
Introduction
·
Section 2:
Project Information
·
Section 3:
Environmental Monitoring Requirement
·
Section 4:
Implementation Status of Environmental Mitigation Measures
·
Section 5:
Monitoring Results
·
Section 6:
Environmental Site Inspection and Audit
·
Section 7: Environmental Non-conformance
·
Section 8:
Future Key Issues
·
Section 9:
Conclusions and Recommendations
(a) construction of approximately 160m long cut-and-cover tunnel and
370m long underwater tunnel between the tunnel section at Ma Tau Kok and the depressed road of the CKR within Kai Tak
Development;
(b) reconstruction of the seawall at Ma Tau Kok
public pier, and the sloping seawall at the Former Kai Tak Airport Runway;
(c) construction of approximately 125m long depressed road and 200m
long underpass of the CKR within Kai Tak Development;
(d) construction of approximately 360m long underground tunnel
ventilation adit of the CKR;
(e) reconstruction of Kowloon City Ferry Pier Public Transport
Interchange; and
(f) other associated works.
Table 2.1 Construction Activities in the reporting month
Locations |
Site Activities |
Kai
Tak |
·
Casting tunnel wall at underpass and ventilation adit; ·
Base slab and wall, roof slab construction at underpass and
depressed road; ·
Backfilling at Underpass ·
Removal of ELS at underpass and depressed road; ·
Falsework erection at underpass |
Ma
Tau Kok |
·
TTM implementation; ·
Pipe piling works for cut and cover tunnel; ·
Rock Excavation; ·
Shotcreting at the Access Shaft; ·
Fresh water pipe installation works; ·
Backfilling at Covered Walkway |
Kowloon
Bay |
·
Excavation for Stage 1 underwater tunnel; ·
S6 Truss fabrication and installation; ·
Concrete packing between wailing and CPP Wall; ·
Roof slab and base slab construction ·
Waterproofing application; ·
Removal of gas pipe line |
Barging
Point |
·
Barging point operation (Spoil Disposal) |
Table 2.2 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
Arup-Mott
MacDonald Joint Venture |
Residential
Engineer (ER) |
Engineer’s Representative |
Mr.
Jeffrey Lau |
2268 3640 |
2268 3954 |
ERM |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker |
Ms. Mandy To |
2271 3313 |
2723 5660 |
Gammon |
Contractor |
Contracts Manager |
Mr. Alan Yan |
2516 8823 |
2516 6260 |
Environmental Manager |
Ms Michelle Tang |
9267 8866 |
2516 6260 |
||
AECOM |
Contractor’s Environmental
Team (ET) |
ET Leader |
Mr. Y T Tang |
3922 9392 |
2317 7609 |
Table 2.3 Status of Environmental Licenses, Notifications and Permits
Permit / License No. / Notification/
Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Further Environmental
Permit |
||||
FEP-01/457/2013/C |
28 Feb 2018 |
End of Project |
Valid |
-- |
Wastewater Discharge
License |
||||
WT00030290-2018 |
22 Mar 2018 |
31 May 2023 |
Valid |
Ma Tau Kok |
WT00030668-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Site Office at
Kai Tak West |
WT00030358-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kai Tak West |
WT00030333-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Barging Point
at Portions 4B & 4C |
WT00030330-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kowloon Bay |
Construction
Noise Permit |
||||
GW-RE0709-20 |
27 Aug 2020 |
26 Feb 2021 |
Valid |
Barging Point Operation at
Kai Tak Barging Point |
GW-RE0603-20 |
4 Aug 2020 |
3 Nov 2020 |
Valid |
Rock Breaking at Ma Tau Kok |
GW-RE0534-20 |
23 Jun 2020 |
21 Dec 2020 |
Valid |
General Works at Kai Tak |
GW-RE0478-20 |
13 Jun 2020 |
12 Dec 2020 |
Valid |
ELS Installation and
Excavation at Stage 1 Underwater Tunnel |
GW-RE0254-20 |
9 Apr 2020 |
30 Sep 2020 |
Valid |
Kai Tak Haul Road |
Chemical Waste Producer Registration |
||||
5118-247-G2347-47 |
30 Jan 2018 |
End of Project |
Valid |
-- |
5118-247-G2347-48 |
30 Jan 2018 |
End of Project |
Valid |
-- |
Marine Dumping Permit |
||||
EP/MD/21-025 |
12 Aug 2020 |
11 Sep 2020 |
Valid until 11 Sep 2020 |
Sediments requiring Type 1
(Dedicated Site) and Type 2 Confined Marine Disposal |
EP/MD/21-049 |
24 Sep 2020 |
23 Oct 2020 |
Valid on 24 Sep 2020 |
|
EP/MD/21-030 |
31 Aug 2020 |
30 Sep 2020 |
Superseded by 20 Sep 2020 |
Sediments requiring Type 3
disposal (Filled up by 70%) |
EP/MD/21-056 |
20 Sep 2020 |
19 Oct 2020 |
Valid on 20 Sep 2020 |
|
Billing
Account for Construction Waste Disposal |
||||
7029909 |
22 Jan 2018 |
End of Project |
Account Active |
-- |
7031949 |
27 Aug 2020 |
26 Nov 2020 |
Account Active |
Billing Account for Disposal of
Construction Waste (by vessels) |
Notification
Under Air Pollution Control (Construction Dust) Regulation |
||||
429442 |
5 Jan 2018 |
5 Jul 2025 |
Notified |
-- |
Monitoring Requirements
Monitoring Equipment
Table 3.1 Air Quality Monitoring Equipment
Tisch
Total Suspended Particulate Mass Flow Controlled High Volume Air Sampler |
|
Calibration
Kit (24-hour
TSP) |
TISCH
Environmental Orifice |
Portable
direct reading dust meter |
Sibata Digital Dust Monitor |
Monitoring Locations
Table 3.2 Location of Construction Dust Monitoring Station
Location |
Monitoring Station |
Description |
E-A14a
[1] |
Block
B of Merit Industrial Centre |
Rooftop
(13/F) |
[1] The air monitoring station
proposed in the EM&A Manual (i.e. Wyler Gardens with ID: E-A14) was not
available for impact dust monitoring, therefore impact monitoring was conducted
at E-A14a as an alternative which was agreed by the ER, IEC and EPD.
Monitoring
Methodology
(a)
The HVS
was installed in the vicinity of the air sensitive receivers. The following criteria were considered in the
installation of the HVS as far as practicable: -
(i)
A horizontal platform with
appropriate support to secure the sampler against gusty wind was provided.
(ii)
Two samplers should
not be placed less than 2m apart from each other;
(iii)
The distance between the HVS and
any obstacles, such as buildings, was at least twice the height that the
obstacle protrudes above the HVS.
(iv)
A minimum of 2 meters separation
from walls, parapets and penthouse for rooftop sampler.
(v)
A minimum of 2 meters separation
from any supporting structure, measured horizontally is required.
(vi)
No furnace or incinerator flues
nearby.
(vii)
Airflow around the sampler was
unrestricted.
(viii)
The sampler was located more than
20 meters from any dripline.
(ix)
Any wire fence and gate, required
to protect the sampler, did not obstruct the monitoring process.
(x)
Permission was obtained to set up
the samplers and access to the monitoring station.
(xi)
A secured supply of electricity
was obtained to operate the sampler.
(b)
Preparation
of Filter Papers
(i)
Glass fibre filters, G810 were
labelled and sufficient filters that were clean and
without pinholes were selected.
(ii)
All filters were equilibrated in
the conditioning environment for 24 hours before weighing. The conditioning
environment temperature was around 25 °C and not variable by more than ±3 °C;
the relative humidity (RH) was < 50% and not variable by more than ±5%. A
convenient working RH was 40%.
(iii)
All filter papers were prepared
and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory
and has comprehensive quality assurance and quality
control programmes.
(c)
Field
Monitoring
(i)
The power
supply was checked to ensure the HVS works properly.
(ii)
The filter holder and the area
surrounding the filter were cleaned.
(iii)
The filter holder was removed by
loosening the four bolts and a new filter, with stamped number upward, on a
supporting screen was aligned carefully.
(iv)
The filter was properly aligned
on the screen so that the gasket formed an airtight seal on the outer edges of
the filter.
(v)
The swing bolts were fastened to
hold the filter holder down to the frame.
The pressure applied was sufficient to avoid
air leakage at the edges.
(vi)
Then the shelter lid was closed
and was secured with the aluminium strip.
(vii)
The HVS was warmed-up for about 5
minutes to establish run-temperature conditions.
(viii)
A new flow rate record sheet was
set into the flow recorder.
(ix)
On site temperature and
atmospheric pressure readings were taken and the flow rate of the HVS was
checked and adjusted at around 1.3 m3/min, and
complied with the range specified in the EM&A Manual (i.e. 0.6-1.7 m3/min).
(x)
The programmable digital timer
was set for a sampling period of 24 hrs, and the starting time, weather condition
and the filter number were recorded.
(xi)
The initial elapsed time was
recorded.
(xii)
At the end of sampling, on site
temperature and atmospheric pressure readings were taken and the final flow
rate of the HVS was checked and recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed
carefully and folded in half length so that only surfaces
with collected particulate matter were in contact.
(xv)
It was then placed in a clean
envelope and sealed.
(xvi)
All monitoring information was
recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance
and Calibration
(i)
The HVS and its accessories were maintained in good working condition, such as
replacing motor brushes routinely and checking electrical wiring to ensure a
continuous power supply.
(ii)
HVSs were calibrated using
TE-5025A Calibration Kit upon installation and thereafter at bi-monthly
intervals.
(iii)
Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in
Appendix E.
(a)
Measuring Procedures
The measuring procedures of the 1-hour dust
meter are in accordance with the Manufacturer’s Instruction Manual as follows:
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the “TIME SETTING” switch to [BG]
(iv)
Push “START/STOP”
switch to perform background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert
the light scattering plate.
(vi)
Leave the equipment for 1 minute upon “SPAN
CHECK” is indicated in the display.
(vii)
Push “START/STOP” switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE
position.
(ix)
Push the “TIME SETTING” switch the time set
in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push “START/STOP” switch to start
measurement.
(b)
Maintenance and
Calibration
(i)
The 1-hour TSP meter was
calibrated at 1-year intervals against a continuous particulate TEOM Monitor,
Series 1400ab. Calibration certificates of the Laser Dust Monitors are
provided in Appendix E.
Monitoring Schedule for the Reporting
Month
Monitoring Requirements
Table 3.3 Noise Monitoring Parameters, Frequency and Duration
Parameter and Duration |
Frequency |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays. Leq, L10 and L90
would be recorded. |
At least once per week |
Table 3.4 Noise Monitoring Equipment for Regular Noise Monitoring
B&K (Model No. 2250-L & 2238) |
|
Acoustic
Calibrator |
B&K (Model
No. CAL21) |
Monitoring Locations
Table 3.5 Noise Monitoring Stations during Construction Phase
Location |
Monitoring Station |
Description |
Measurement |
E-N12a [1] |
19 Hing Yan Street |
Rooftop (9/F) |
Façade |
E-N21a [1] |
Block B of Merit Industrial Centre |
Rooftop (13/F) |
Free field[2] |
Notes:
[1] The noise monitoring stations proposed in the
EM&A Manual (i.e. Grand Waterfront Tower 3 with ID: E-N12 and Hang Chien Court Block J with ID: E-N21) were not available for impact
noise monitoring, therefore impact monitoring was conducted at E-N12a and
E-N21a as an alternative which was
agreed by the ER, IEC and EPD.
[2] A
correction of +3 dB(A) was made to the free field measurements.
Monitoring
Parameters, Frequency and Duration
Table 3.6 Noise Monitoring Parameters, Frequency and Duration
Location |
Parameter and Duration |
Frequency |
E-N12a and E-N21a |
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would
be recorded. |
At
least once per week |
Monitoring Methodology
(a)
The sound level meter was set on
a tripod at a height of 1.2 m above the ground.
(b)
Façade measurement was made at E-N12a.
(c)
Free field measurements was made at monitoring location E-N21a. A correction of +3
dB(A) shall be made to the free field measurements.
(d)
The battery condition was checked to ensure the correct
functioning of the meter.
(e)
Parameters such as frequency
weighting, the time weighting and the measurement time were set as follows:
(i)
frequency weighting
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes) during non-restricted
hours i.e. 0700 – 1900 on normal weekdays.
(f)
Prior to and after each noise
measurement, the meter was calibrated using the acoustic calibrator for 94
dB(A) at 1000 Hz. If the difference in
the calibration level before and after measurement was more than 1 dB(A), the
measurement would be considered invalid and repeat of noise measurement would
be required after re-calibration or repair of the equipment.
(g)
During the monitoring period, the
Leq, L10 and L90
were recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(h)
Noise measurement was paused
during periods of high intrusive noise (e.g. dog barking, helicopter noise) if
possible. Observations were recorded when intrusive noise was unavoidable.
(i)
Noise monitoring was cancelled in
the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind
with gusts exceeding 10m/s.
(a)
The
microphone head of the sound level meter was cleaned with soft
cloth at regular intervals.
(b)
The meter
and calibrator were sent to the supplier or HOKLAS laboratory to check and
calibrate at yearly intervals.
(c)
Calibration
certificates of the sound level meters and acoustic calibrators are
provided in Appendix E.
Monitoring Schedule for the Reporting
Month
Table 3.7 Water Quality Monitoring Equipment
Equipment |
Brand and Model |
Detection Limit |
Dissolved Oxygen
Meter |
YSI 6820 V2 |
0 – 20 mg/L 0-200% saturation |
Water Temperature
Meter |
0-45 degree
Celsius |
|
Salinity Meter |
0-40 parts per
thousand (ppt) |
|
Turbiditimeter |
0-1000 NTU |
|
pH meter |
pH 0.0 to 14.0 |
|
Water Sampler |
Kahlsico Water Sampler |
N.A |
Echo Sounder |
Eagle Cuda-168 |
N.A |
Global
Positioning System |
JRC DGPS 224
Model JLR-4341 with J-NAV 500 Model NWZ4551 |
N.A |
Table 3.8 Impact Water Quality Monitoring Stations
Type of Station |
Station |
Location |
Easting |
Northing |
Water
Quality Monitoring Station |
IS1 |
Planned Kai Tak Cooling Water Intake (subject to its
implementation) |
839050 |
819377 |
IS2 |
To Kwa Wan Typhoon Shelter |
838450 |
819399 |
|
IS3 |
Tai Wan Salt Water Intake |
837948 |
818202 |
|
Control
Station |
C1 |
Control
Station 1 |
837787 |
817712 |
C2 |
Control
Station 2 |
838237 |
818804 |
|
C3 |
Control
Station 3 |
839105 |
819019 |
Table 3.9 Water Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
Dissolved Oxygen, Temperature, Turbidity,
pH value, Salinity, Suspended Solids, Copper and Total PAHs |
Three days per week, at mid-flood and mid-ebb tides |
All monitoring equipment were
checked and calibrated before use. Responses of sensors and electrodes were
also checked with certified standard solutions before each use.
The interval between 2 sets of
monitoring was not less than 36 hours.
Individual flood and ebb tides
not less than 0.5m.
At least 3 replicate in-situ measurements
and water sampling were carried out in each sampling event.
Measurements were taken at 3 water
depths, namely 1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth station may be omitted. Should the water depth be less than 3m, only
the mid-depth station was monitored.
Analysis of suspended solids was
carried out by ALS Technichem (HK) Pty Ltd. Sufficient water
samples were collected at the monitoring stations for carrying out the laboratory
analysis. The analysis followed the standard methods as described in APHA
Standard Methods for the Examination of Water and Wastewater, 19th Edition
(APHA 2540D for SS).
Analysis of copper was carried
out by ALS Technichem (HK) Pty Ltd. Sufficient water
samples were collected at the monitoring stations for carrying out the
laboratory analysis. The analysis followed the standard methods as described in
USEPA Method for inductively coupled plasma-mass spectrometry (ICP-MS),
Revision 1 (ICP-MS USEPA 6020A for copper).
Analysis of total polycyclic
aromatic hydrocarbon (PAHs) was carried out by ALS Technichem
(HK) Pty Ltd. Sufficient
water samples were collected at the monitoring stations for carrying out the
laboratory analysis. The analysis followed the standard methods as described in
USEPA Methods for Gas Chromatography-Mass Spectrometry Detector, Revision 3,
(GC-MSD USEPA 3510C,USEPA 3630C,USEPA 8270C for total
PAHs).
Water samples for suspended
solids measurements were collected in high density polythene bottles, packed in
ice (cooled to 4oC without being frozen), and delivered to a HOKLAS
laboratory as soon as possible after collection.
Monitoring Schedule for the
Reporting Month
Table 4.1 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission
Date |
Condition 3.4 of |
Monthly EM&A Report for
August 2020 |
14 September 2020 |
Table 5.1 Summary of 24-hour
TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
36.9 |
22.3 – 54.1 |
197.3 |
260 |
Table 5.2 Summary of 1-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
61.0 |
57.4 – 63.2 |
302.4 |
500 |
Table 5.3 Summary of Construction Noise Monitoring Results in the Reporting Period
ID |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
E-N12a |
65.8
– 68.1 |
75 |
E-N21a |
65.0
– 68.3 |
75 |
Table 5.4 Summary of Impact Water Quality Monitoring Results
Locations |
Parameters |
||||||||||
Temperature (oC) |
pH value |
Dissolved Oxygen
(mg/L) |
Turbidity (NTU) |
Salinity (ppt) |
Suspended Solids1
(mg/L) |
Copper1 |
Total PAHs1 (µg/L) |
|
|||
Surface &
Middle |
Bottom |
|
|||||||||
CS1 |
Avg. |
28.06 |
8.14 |
5.62 |
5.46 |
3.18 |
31.59 |
3.69 |
- |
- |
|
Min. |
24.42 |
7.90 |
4.70 |
4.59 |
2.04 |
29.87 |
2.30 |
- |
- |
|
|
Max. |
29.29 |
8.34 |
6.54 |
6.20 |
4.60 |
34.46 |
7.20 |
- |
- |
|
|
CS2 |
Avg. |
28.09 |
8.15 |
5.57 |
5.49 |
3.25 |
31.50 |
3.89 |
- |
- |
|
Min. |
24.66 |
7.87 |
4.64 |
4.62 |
1.81 |
29.91 |
2.27 |
- |
- |
|
|
Max. |
29.29 |
8.36 |
6.21 |
6.14 |
5.51 |
34.04 |
8.61 |
- |
- |
|
|
CS3 |
Avg. |
28.10 |
8.14 |
5.67 |
5.61 |
3.41 |
31.46 |
3.73 |
- |
- |
|
Min. |
24.72 |
7.88 |
4.63 |
4.63 |
1.81 |
30.05 |
2.29 |
- |
- |
|
|
Max. |
29.29 |
8.37 |
6.35 |
6.23 |
5.80 |
33.88 |
8.32 |
- |
- |
|
|
IS1 |
Avg. |
28.11 |
8.15 |
5.65 |
5.60 |
3.58 |
31.44 |
3.82 |
- |
- |
|
Min. |
24.77 |
7.89 |
4.64 |
4.64 |
1.69 |
29.94 |
2.28 |
- |
- |
|
|
Max. |
29.29 |
8.38 |
6.31 |
6.24 |
6.51 |
33.73 |
7.97 |
- |
- |
|
|
IS2 |
Avg. |
28.11 |
8.15 |
5.67 |
5.62 |
3.37 |
31.43 |
3.85 |
- |
- |
|
Min. |
24.79 |
7.89 |
4.63 |
4.61 |
1.80 |
29.91 |
2.06 |
- |
- |
|
|
Max. |
29.30 |
8.38 |
6.23 |
6.16 |
6.54 |
33.67 |
10.06 |
- |
- |
|
|
IS3 |
Avg. |
28.07 |
8.15 |
5.55 |
5.42 |
3.40 |
31.56 |
3.94 |
- |
- |
|
Min. |
24.55 |
7.87 |
4.62 |
4.60 |
2.20 |
29.94 |
1.76 |
- |
- |
|
|
Max. |
29.29 |
8.36 |
6.23 |
6.10 |
5.12 |
34.26 |
9.52 |
- |
- |
|
|
Note: |
|
||||||||||
1.
Some of laboratory
results of Copper and Total PAHs in September 2020 were in progress, the
summary for those parameters will be reported in next reporting period. |
Table 5.5 Summary of Water Quality Exceedances
Exceedance Level |
DO (S&M) |
DO (Bottom) |
Turbidity |
Suspended Solids |
Copper1 |
Total PAHs (µg/L)1 |
|
|||||||
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
|
||
IS1 |
Ebb |
0 |
0 |
0 |
0 |
0 |
3 |
2 |
0 |
1 |
0 |
0 |
0 |
|
Flood |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
2 |
1 |
0 |
0 |
0 |
|
|
IS2 |
Ebb |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
1 |
0 |
0 |
0 |
|
Flood |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
1 |
0 |
1 |
0 |
0 |
|
|
IS3 |
Ebb |
0 |
0 |
0 |
0 |
0 |
1 |
2 |
0 |
1 |
0 |
0 |
0 |
|
Flood |
0 |
0 |
0 |
0 |
2 |
1 |
1 |
1 |
1 |
0 |
0 |
0 |
|
|
|
Total |
0 |
0 |
0 |
0 |
4 |
8 |
8 |
4 |
5 |
1 |
0 |
0 |
|
|
||||||||||||||
1.
Some of laboratory results of Copper and Total PAHs in September 2020 were in
progress, the summary for those parameters will be reported in next reporting
period. |
||||||||||||||
|
Table 6.1 Observations and Recommendations
of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air Quality |
9 September 2020 |
Reminder: · The Contractor was reminded to replace the improper NRMM
label on the excavator at Ma Tau Kok and Covered
Walkway to comply the requirement of APCO. |
The item was rectified by the Contractor on 11 September 2020. |
16 September 2020 |
Reminder: · The Contractor was reminded to replace the decolored NRMM label on the excavator at Kai Tak. |
The item was rectified by the Contractor on 17 September 2020. |
|
30 September 2020 |
· NRMM label was not observed on the excavator at Covered
Walkway. The Contractor was reminded to affix the NRMM label on the excavator. |
The item was rectified by the Contractor on 5 October 2020. |
|
Noise |
2 September 2020 |
· Noise emission label (NEL) was not observed on the
hand-held breaker at C&C tunnel area. The Contractor was reminded to
affix the NEL on the hand-held breaker. |
The item was rectified by the Contractor on 4 September 2020. |
Water Quality |
2 September 2020 |
· Muddy trail was observed outside the site entrance of
Covered Walkway. The Contractor was reminded to provide adequate wheel
washing facility for vehicle at the site entrance. |
The item was rectified by the Contractor on 4 September 2020. |
30 September 2020 |
· Oil drums were observed stored without secondary
containment at Kai Tak. The Contractor was reminded to provide a secondary
containment for oil drums. |
The item was rectified by the Contractor on 5 October 2020. |
|
Waste/ Chemical Management |
2 September 2020 |
· Some of chemicals was observed stored without drip tray at
Ma Tau Kok and Kai Tak Barging Point. The
Contractor was reminded to provide a secondary containment for chemical
storage. |
The item was rectified by the Contractor on 4 September 2020. |
9 September 2020 |
· Chemicals were stored without a drip tray at Ma Tau Kok and Depressed road. The Contractor was reminded to
provide a drip tray for chemical storage. |
The item was rectified by the Contractor on 11 September 2020. |
|
23 September 2020 |
· Chemicals were observed stored without secondary
containment at Ma Tau Kok. The Contractor was
reminded to provide a secondary containment for chemical to prevent
accidental spillage. |
The item was rectified by the Contractor on 25 September 2020. |
|
Landscape & Visual |
Nil |
Nil |
Nil |
Permits/ Licenses |
Nil |
Nil |
Nil |
Table 8.1 Construction Activities in the coming three months
Locations |
Site Activities |
Kai
Tak |
·
Base slab and wall,roof slab construction at cut &
cover, underpass and depressed road; ·
Backfilling works and ELS removal at cut & cover,
underpass and depressed road; ·
Dismantle of working platform |
Ma
Tau Kok |
·
TTM implementation; ·
Rock excavation; ·
Pipe piling works for cut and cover tunnel; ·
Fresh water pipe installation works; ·
Constrcution of MTK east wall; ·
Constrcution of traffic deck; ·
Covered walkway construction ·
Relocation of MTK public pier |
Kowloon
Bay |
·
Backfilling and ELS removal works; ·
Roof slab, base slab and wall construction; ·
Removal of gas pipe line; ·
Waterproofing application |
Barging
Point |
·
Barging point operation (Spoil Disposal) |